PHS stadium committee pushes for aluminum bleachers

By Gwen Sour 4 min read

PARKERSBURG -- The Wood County Board of Education voted Tuesday to advance a revised plan for Parkersburg High School's Stadium Field visitor bleachers while also seeking a schematic design of an alternative proposed by the stadium committee.

The approved motion calls for moving toward bidding Pickering Associates' revised plan, with safety upgrades and parking renovations as alternates, and developing the committee's proposal for comparison. The action did not award a construction contract or settle which design ultimately will be built.

Ryan Taylor, CEO of Pickering Associates, presented a revised design intended to reduce costs by retaining portions of the existing concrete structure. The stadium committee urged the board to consider replacing the visitor stands with aluminum bleachers and using potential savings for other improvements.

Board member Simon Hargus proposed adding the committee's concept to the work authorized Tuesday, saying the two approaches could be evaluated without abandoning progress on the project.

"This amendment allows us to compare a couple ideas," he said.

Taylor said his firm could develop a schematic showing the alternative's footprint, wall heights and other details. Earlier in the meeting, he said work on the existing proposal could be slowed enough to allow the board to compare the options before bidding.

"We would want to make sure that you fully understand what you're getting into," Taylor said.

Under the revised concrete plan, crews would remove the upper portion of the visitor stands, leaving a seating section about 300 feet long with 10 rows. New precast concrete treads and risers would be placed over existing concrete, with supporting girders reinforced.

Taylor said retaining that concrete would reduce demolition costs compared with the approach used during earlier stadium work. Other changes would retain end walls and add interior railings to address safety concerns, reduce work beneath the stands and attempt to preserve the existing concrete slab for use in the parking area.

The proposal also would open additional space behind the school, improve drainage and provide more parking, including accessible spaces. Security improvements include extended fencing, a permanent guardhouse and a more secure rear campus entrance.

Taylor described potential cost-saving alternatives involving the rear wall's brick finish and decorative windows.

Speaking for the stadium committee, Wood County Commissioner Jim Hamric presented a list of priorities led by aluminum bleachers with approximately 2,900 seats in the existing footprint. The committee wants a brick facade facing the school and fencing and gates with a wrought-iron appearance beneath the stands.

Hamric said committee members had struggled with the idea of giving up the existing concrete but concluded replacement offered a better opportunity to address the stadium's other needs.

"The next alternative is to spend our money wisely on the next best thing," he said.

The committee's priorities also include restroom renovations, a visitor locker room large enough for a 60-member team, concession improvements, LED lighting and better field drainage. Hamric said the group voted 11-0 Monday to support the proposal and prioritized list.

Board member Debbie Hendershot questioned the shift toward aluminum bleachers and said alumni she consulted favored preserving the concrete.

Stadium committee President Pat McFarland said the group reached a consensus in 2018 that replacing the concrete stands was the more economical approach. He said members had consulted architects, engineers and contractors and concluded that preserving the concrete would leave less money for other improvements.

"You can spend all kinds of money to try to maintain some of that existing concrete and brick, but you're going to give up all this other stuff that we think … is important," McFarland said.

McFarland said he had heard similar preferences for preserving the concrete, but many people became receptive to replacement after learning about the costs and trade-offs. He also said the committee's meetings are open to the public and held at 7 p.m. on the first Wednesday of each month in the PHS cafeteria.

Taylor's proposed schedule targets advertising for bids Jan. 18, allowing about six weeks for bidding and negotiating a contract in March. Construction could begin in spring 2027, with completion targeted for May 2028, depending on the board's decisions.