Parkersburg Planning Commission advances generator amendment
Says primary source of electricity must be utility
Trending
PARKERSBURG --S The Municipal Planning Commission on Friday approved an amendment to Parkersburg's zoning code prohibiting people from using generators as their primary source of electricity, except in cases of temporary power loss.
City Planner Connor LaVelle said the change was requested by the code enforcement department, which has encountered situations where people are living in houses without electrical service and "running those generators 24/7."
"This will help curb some serious issues that they've been running into," he said.
Commission member Sean Andrews asked if a house without electrical service would be considered uninhabitable. LaVelle said there may be some situations - such as a fire that damages the electrical service without damaging a large portion of the house - where people could remain in the structure.
"We don't have a code that says you can't" use a generator as a primary source of power, LaVelle said.
Commission Vice President Eric Gumm said he'd discussed the issue with Code Director Andy Nestor in a subcommittee meeting and "I was just really shocked at the level of frequency that it was happening."
Parkersburg Fire Chief Jason Matthews, who was not at the meeting, said the department has seen several incidents where sustained use of generators can cause problems. Improper refueling can lead to spills that cause fires or generators in basements can "fill up the house with carbon monoxide," he said.
In cases where people are using a generator as a temporary power source during an outage, "we don't really see a lot of issues there," Matthews said.
The ordinance would require primary electrical service to a building to come from a utility company or municipal electric provider. Wind and solar collection systems could supplement them.
Diesel, natural gas and propane-fueled generators could be used during planned or unplanned temporary losses of electricity. The use would be limited to 10 days unless an extension is granted by the chief code official.
The idea is to keep people from using generators indefinitely after electrical service has been shut off for non-payment.
"This could also be an impediment to squatters," Assistant City Attorney Rob Tebay said.
LaVelle said making it part of the zoning code would allow people who wanted to use solar power as their primary source of electricity to seek a variance from the Board of Zoning Appeals.
LaVelle said some city officials had discussed including a provision to limit the use of generators between 7 p.m. and 7 a.m., in line with the city's noise ordinance. But most commission members were resistant to that idea.
"This is for somebody that really, truly has an emergency?" commission member John Reed said. "To tell them they have to shut it off at 7 p.m. is a little strict."
LaVelle said the code director could grant an extension in that case too or the guidelines could be changed. Ultimately, no motion was made to include a time limit, and the commission voted 8-0, with three members absent, to refer the ordinance to Parkersburg City Council.
Evan Bevins can be reached at ebevins@newsandsentinel.com