Trending
PARKERSBURG -- The Wood County Commission wrapped up its discussions Monday with the final three architectural and engineering firms to see who they want to work with on building a possible new county building in downtown Parkersburg.
Commissioners met with representatives from Pickering Associates of Parkersburg, Edward Tucker Architects of Huntington and Alpha Architects and Engineers of Morgantown. The commission also met with companies last week.
"We are trying to create an asset to cover some of the things we needed during the pandemic," Commission President Blair Couch said. "We want it to be a generational change to downtown Parkersburg."
The county has been looking at possible uses for the 170-by-170 foot lot, the site former county jail, including a possible new 911 center, housing the county maintenance department, and providing a large meeting room/emergency shelter and storage.
However, 911 officials have stated they did not want to be in downtown and that aspect of the project may change, but county officials still want to look at something for the maintenance department, record storage and a large meeting space that still allows for social distancing.
Commissioners said the old building that still houses the maintenance department and once housed the sheriff's department would remain up and until the new building is built, then it will be demolished for parking spaces.
The county is scheduled to receive $16.2 million from the American Recovery Act and money from opioid abuse settlements that could go into this project.
County Engineer Maria Hardy also sat in on the interviews to ask questions.
Ryan Taylor, president and CEO of Pickering Associates, said it is a local firm with a lot of experience around the state, including many 911 centers and garages for the Ohio Department of Transportation.
"Everyone who would be working on this job would be coming from the Mid-Ohio Valley," he said.
The garages dealt with tearing down existing facilities and building new which included vehicle work bays, storage and office space which is what officials have said they want for this facility, said Traci Stotts, vice-president of marketing and development.
With meeting spaces, Stotts said they look at the acoustics of the space in terms of materials to make sure the space is functional and meets the need of those using the space.
"The project is a lifecycle from start to finish," Taylor said. "We are running these jobs from start to finish with someone always there."
Officials with Edward Tucker Architects said they do not have in-house engineers and they put together teams of people for each job. They brought representatives from CMTA Engineering of Lexington, Ky., and Schaefer Structural Engineers of Cincinnati.
"It gives us the ability to look at the strengths of each consultant that we work with and tailor them to the team for that specific project," said Phoebe Randolph of Edward Tucker Architects.
She wanted to hear more from county officials about what their goals are for the project.
They are doing window replacement projects at a number of Wood County Schools.
Randolph said they would like six to eight months to design the project. It could be sooner, but they want the time to interact with everyone involved.
Rick Colebank, president and COO of Alpha, said it has engineers, architects, landscape designers and more. It has done local projects.
Rebecca Key, director of Architecture for Alpha, said they will be talking to people with a stake in it as they design it, knowing what the space will be used for and how it will be put together.
Colebank said they like to have six to eight months to work out a design.
"It just takes time to work out what you need in that facility," he said. "The only way to do that is to sit down and talk to people, bring options to them and bounce ideas off of each other."
County officials talked about what each firm's workload was and their availability. They discussed whether it was wiser to quickly move or wait and see if the demand for building materials would decrease. They also asked if they would be willing to use local labor.
"We know there will be a lot of moving pieces to this with a lot of community buy-in," Couch said. "There are so many things that will go into this and it will take a firm to have a lot of discussions on this."
Contact Brett Dunlap at bdunlap@newsandsentinel.com