Flicker of Hope: Pleasants Power retirement delayed again as potential buyer considers purchase
Trending
CHARLESTON -- The retirement of the Pleasants Power Plant has been delayed after a potential buyer came forth, the owners said.
The plant that has operated more than 40 years was set for retirement on Thursday.
According to a letter from Akron-based Energy Harbor to PJM Interconnection, the company said it intends to keep the Pleasants Power Plant operational through July while negotiations continue between Texas-based Energy Transition and Environmental Management and other companies regarding the future of the plant.
According to the letter, Energy Harbor is seeking to change the status of Pleasants Power's two coal-fired units from "retired" to "mothballed." The company estimates that the mothballed status would continue through July 31. The deactivation date set for Thursday would remain unchanged.
According to PJM, "a mothballed unit is a generating unit placed on inactive status for a defined amount of time." PJM is a wholesale energy transmission company serving 13 states and Washington, D.C. It includes 400 member utilities and independent power producers.
Speaking by phone Thursday morning, Pleasants County Commission President Jay Powell said he was cautiously optimistic, having seen the plant saved multiple times from retirement over the last several years.
"Every layer of this onion has been peeled. It's been dead and resurrected over and over again. It's been a roller coaster ride," Powell said. "Obviously, this is not a done deal yet. We can't celebrate yet. But what it speaks to is this: the fact that they have some serious inquiries going on to the point they feel comfortable removing that retirement status to mothballing … that is the big deal."
Energy Harbor, formerly FirstEnergy Solutions, announced last March it would close Pleasants Power beginning May 31. It sold the plant to ETEM for demolition while leasing the plant and burning off its remaining coal stockpiles.
Pleasants Power, located south of St. Marys and Belmont near the Wood County border, has been on the chopping block since 2018 when the plant was first slated to be shut down. Deactivation of the plant was moved to 2022, but put on hold in 2019 after the Legislature passed a bill in a special session to provide FirstEnergy Solutions a $12.5 million annual break in Business and Occupation Taxes for the plant.
Both of Pleasants Power's units went online 42 years ago. The 1,300 megawatt, coal-fired power plant directly employs 154 workers and thousands of temporary union workers during maintenance periods with a $400 million economic impact for Pleasants County and the surrounding Mid-Ohio Valley.
"At this point in time, the Pleasants Power Plant celebrates every victory," Powell said in an additional statement. "Make no mistake, yesterday's statement to PJM can be game changing. Although we realize the battle isn't won yet, this is a critical step."
The plant is being considered by two different potential buyers. Two FirstEnergy Corp. subsidiaries, Monongahela Power Co. and Potomac Edison Co., are in talks with ETEM to lease the plant for a 12-month period while it considers closing another power plant in the state and buying Pleasants Power. The plant would no longer produce power, but Mon Power/Potomac Edison would keep the 154 workers employed and keep the plant functional should the companies decide to purchase it.
Any letter of intent between the companies and ETEM would have to be approved by the West Virginia Public Service Commission, including a potential $36 million temporary surcharge on Mon Power/ Potomac Edison residential and commercial customers in North Central West Virginia and the Eastern Panhandle, though the companies said the final temporary surcharge request could be more due to unforeseen costs.
A new potential buyer came into the picture last week. According to PSC filings, California-based Omnis Fuel Technologies is also in talks with ETEM to buy Pleasants Power. Omnis wants to use Pleasants Power to produce hydrogen using hydrocarbons with low or net-zero greenhouse gas emissions. Hydrogen is a clean fuel that can be used to decarbonize manufacturing processes, such as steel and metals production, and heavy transportation.
"On behalf of Pleasants County, we remain cautiously hopeful that there is a long-term future for this plant," Powell said. "We will continue to work hard and pray harder that a complete resolution will be coming forward soon."
Steven Allen Adams can be reached at sadams@newsandsentinel.com.